Highland High School

Highland High School

Highland High School, originally opened in 1956, is a cornerstone of the Sugar House community. Highland serves 1,883 students in grades 9–12, whose families speak 29 different languages. The new school will be built on the north side of the campus, so students can continue learning in the current building while the new school is under construction.

  • Estimated cost: $300 M
  • Length of construction: 46-48 months
  • Estimated completion: 2030
aerial picture of foundations for new Highland High

September 9, 2026

UPDATE: September 1 - The New Highland Is Taking Shape

Foundations and footings for the new theater and orchestra pit are almost complete, while crews continue construction work throughout the site. We appreciate the patience of Highland students and

UPDATE: April 7 - Construction Begins

April 29, 2026

UPDATE: April 7 - Construction Begins

 The north and east parking lots are now closed as crews have begun installing construction fencing and completing preliminary work for the new school this week. When students return from Spring

Update: Highland High School – March 3, 2026

March 17, 2026

Update: Highland High School – March 3, 2026

Construction is moving forward on several projects. We expect to break ground at Highland High School in April. Student athletes are already adjusting to temporary practice locations: Highland

Update: February 12, 2026

March 6, 2026

Update: February 12, 2026

Planning for the rebuild is in its final stages. Construction fencing is going up and utility work is scheduled to begin in

Update: Status of Asphalt Project  -July 1, 2025

July 31, 2025

Update: Status of Asphalt Project -July 1, 2025

Crews are currently digging and removing dirt and asphalt on the south end of campus to prepare the area for additional parking and lighting that will support construction activities in spring 2026.

Highland High School Rebuild Details

  • Total Estimated Budget: $300 million
  • Estimated Groundbreaking: April-May 2026
  • Construction Timeline: 46-48 months
  • Estimated Completion: 2030