It’s all about walls this week at both construction sites.
Highland High School
In the southeast part of the building, crews are putting up concrete block for interior classroom walls. On the rest of the site, work continues on the footings and foundations that will support the new school.
West High School
The tallest wall sections so far were put into place this week. These tilt-up walls stand 76 feet tall and will enclose the auditorium and the catwalk. Elsewhere on the site, the steel structure for the commons and entrance is going up, and concrete is being poured for the athletic field house on the south end of the site.